What planning method for basic dates do you use?
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements.
What planning method for basic dates do you use?
A . Free planning
B . Top-down
C . Strict bottom-up
D . Bottom-up
Answer: D