What do you have to consider?

You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order.

What do you have to consider?
A . The maintenance orders must be assigned to WBS element.
B . The maintenance order s must be assigned to the same budget profile as the project definition.
C . The maintenance orders must be assigned as sub-networks.
D . The maintenance orders must be assigned to the same plant as the network.

Answer: D