Cost & Budget

Cost & Budget

You are using network and internal activities in your project. You have already create a purchase requisition and the bid invitation., and have entered the quotation …

What is the typical sequence for the following business transactions and document.
A . Benefic check – Acceptance of performed service- vendor selection – purchase order handing- purchase order monitoring-Good receipt – invoce ..
B . Vendor selection – purchase order handing- purchase order monitoring- Benefic Check-Acceptance of performed services.
C . Vendor selection – purchase order handing – invoice receipt – purchase order monitoring -Good receipt.
D . Vendor selection- Purchase order handing-purchase order monitoring-Good receipt-Invoice receipt.

Answer: D

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments