What is the shortest number of days in which the project can be completed?

Refer to the exhibit.

The figure below shows the network diagram for the activities of a large project.

What is the shortest number of days in which the project can be completed?
A . 21 days.
B . 22 days.
C . 27 days.
D . 51 days.

Answer: C