What do you recommend for milestone definition?
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling.
What do you recommend for milestone definition?
A . Enter an offset of -18 days to the finish date of the activity
B . Enter February 10 as fixed date
C . Enter 10 days as duration
D . Enter an offset of 10 days to the start date of the activity
Answer: B
Latest C_TS412_1909 Dumps Valid Version with 112 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
                             Subscribe
                            
                        
                                            
                             Login                        
                    
                        0 Comments                    
                                        
                     Inline Feedbacks                    
                    View all comments