One of the fist stages of designing a Partnership is to come up with joint KPIs. These
One of the fist stages of designing a Partnership is to come up with joint KPIs. These
should be:
A . Measurable, achievable and time-bound
B. Relatable, specific and measurable
C. Time bound, difficult and relevant
D. Significant, measurable and achievable
Answer: A
Explanation:
The correct answer is Measurable, achievable and time-bound. This is from SMART KPIs on p. 151. Smart stands for specific, measurable, achievable, relevant, time-bound. In the exam they come up in different orders so be careful.