What are these four categories?

According to Mendelow, there are four ways stakeholders can be managed, depending on the amount of power they have, and how interested they are in your project .

What are these four categories?
A . Keep satisfied, keep informed, minimal effort, no effort
B. Manage closely, manage loosely, keep satisfied, keep informed
C. Minimal effort, manage closely, keep informed, keep satisfied
D. Keep informed, keep happy, keep satisfied, keep notified

Answer: C

Explanation:

The four categories are; Minimal effort, manage closely, keep informed, keep satisfied. You can see the Matrix on p.81. An easy way to remember this is there are 2 Ms and 2 Keeps. And these sit on opposite sides of the matrix.