Who typically participates as the ART’s Business Owners to approve the team’s PI Objectives?
Who typically participates as the ART’s Business Owners to approve the team’s PI Objectives?
A . Product Owners
B. System Architects
C. Product Management
Answer: C
Explanation:
Read more: https://www.scaledagileframework.com/product-management/