Communicating the Vision to the Agile Release Train during Program Increment Planning supports which SAFe Core Value?
Communicating the Vision to the Agile Release Train during Program Increment Planning supports which SAFe Core Value?
A . Program Execution
B. Alignment
C. Transparency
Answer: B
Explanation:
Read more: https://www.scaledagileframework.com/safe-core-values/