Which two additional steps must be taken to bring the additional ports online?
You are deploying an 8-node AFF A700 by using BES-53248 cluster switches. During the installation, you notice that ports higher than 16 are not coming online. You verify that the additional licenses are installed.
Which two additional steps must be taken to bring the additional ports online? (Choose two.)
A . Reload the firmware
B. Reload the RCF file
C. Re-enable each port
D. Reload the switch
Answer: B,D
Explanation:
Reference: https://thinksystem.lenovofiles.com/storage/help/index.jsp?topic=%2Fhw-sw-ix8-setup%2F43A528F5-967F-432E-94CE-89A38234A8DC_.html