Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)

Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)
A . Risks on the teams’ planning boards are resolved by the Release Train Engineer
B. Teams use color-coding for their backlog items as a reminder that they are re-quired to have all backlog item types on their planning boards
C. Draft objectives and uncommitted objectives are written
D. All teams’ planning boards are visible and use the same color-coding
E. Draft objectives are written but do not include exploration Enablers

Answer: C,D

Latest SAFe-RTE Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments