What are two key areas a Release Train Engineer should focus on to support a successful PI Planning event?

Program Increment (PI) Planning is a major event that requires preparation, coordina-tion, and communication.

What are two key areas a Release Train Engineer should focus on to support a successful PI Planning event? (Choose two.)
A . Organizational readiness – Strategic alignment; roles, teams, and train setup
B. Architectural readiness – Defining the Architectural Runway
C. Operational readiness – Facilitating PI events such as scrum of scrums, Iteration Planning, and System emo
D. Facilities readiness – Space and logistics for the event
E. Process readiness – The operational rhythm that enables SAFe governance

Answer: A,D

Latest SAFe-RTE Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments