The team’s draft plan review consists of which three items at the end of the first day of the Program Increment (PI) Planning event? (Choose three.)

The team’s draft plan review consists of which three items at the end of the first day of the Program Increment (PI) Planning event? (Choose three.)
A . Capacity and load estimates (Correct)
B. Program delivery schedule
C. Draft PI Objectives
D. Risks and impediments
E. Iteration Goals
F. Refined team backlogs

Answer: A,C,D

Latest SAFe-RTE Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments