Which three statements best describe the purpose of having a Definition of Done? (Choose three.)

Which three statements best describe the purpose of having a Definition of Done? (Choose three.)
A . It is a checklist to monitor the Development Team member’s progress on a task.
B . It provides guidance to the Development Team when they are forecasting their Sprint Backlog during the Sprint Planning.
C . As the Development Team is doing the work, it provides guidance on the remaining work needed to create the potentially shippable Increment by the end of the Sprint.
D . It helps the Development Team defer any pending work to subsequent Sprints.
E . It creates transparency and provides a common understanding of the ‘done’ state of the Increment at the Sprint Review.
F . It helps the Scrum Team decide how much time is needed before the Sprint can end.

Answer: BCE

Explanation:

When a Product Backlog item or an Increment is described as ‘Done’, everyone must understand what

‘Done’ means. Scrum Team members must have a shared understanding of what it means for work to be complete, to ensure transparency and is used to assess when work is complete on the product Increment. This Definition of Done provides the team guidance on what it takes to make the increment shippable.