Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question

Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question
A . Basic dates
B. Forecast dates
C. Baseline dates
D. Planned dates

Answer: A,B