What controls whether the delivery date is defined by the earliest or latest scheduled dates?

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity.

What controls whether the delivery date is defined by the earliest or latest scheduled dates?
A . The network profile
B. The control key
C. The table of MRP controllers
D. The scheduling parameters for the network

Answer: D