What is the requisites for implement scheduling of events?

Material

Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events.

What is the requisites for implement scheduling of events?
A . Priority of events must be set.
B. Scheduling parameters for material scheduling must be set.
C. Events must be released manually.
D. Event scenarios must be defined.

Answer: D