Which of the following is the best report that he can use to ensure Time Estimation and Time Spent by his team on issues are on track?

As a project manager, Dom is responsible in monitoring all issues that have been assigned to his team are on track and the Time Estimation for each issue is correctly measured.

Which of the following is the best report that he can use to ensure Time Estimation and Time Spent by his team on issues are on track?
A . Single Level Group By Report
B. Pie Chart Report
C. Resolution Time Report
D. Time Tracking Report
E. Average Age Report
F. Time Since Issues Report

Answer: D

Explanation:

Time Tracking Report shows the original and current time estimates for issues in the current project. This can help users determine whether work is on track for those issues.

– Identify which issues have exceeded the original estimation.

– Identify which issues are still on track.

– Identify which issues are correctly measured.

– Identify accuracy of the overall time estimation.

– Identify the current team’s progression on issues that they are currently working on.

Latest ACP-620 Dumps Valid Version with 150 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments