Which of the following are true about parallel sprints?

Razi’s team and Dom’s team are working on the same backlog, but they have their own active sprint.

Which of the following are true about parallel sprints? (Choose three.)
A . If users want to complete active sprint A with unresolved issues, they cannot move it to active sprint B.
B. Project administrators can disable the parallel sprint feature for their projects.
C. Users cannot complete multiple active sprints at once.
D. Users can run up to 2 parallel sprints only.
E. Users cannot have a separate velocity chart for each team.

Answer: A,C,E

Explanation:

The parallel sprints feature lets users enable multiple active sprints that are running parallel to each other. For example, if they have two teams working on the same backlog, each team can now work on their own active sprint simultaneously.

Users can only complete one sprint at a time.

Atlassian does not mention whether there are limits on how many sprints users can run in parallel, however it is possible for users to run more than two parallel sprints.

Users cannot have a separate velocity chart for each team.

Sprint feature can be enabled/disabled from the global settings. Only Jira administrators have access to control it.

If there are unresolved issues in the current active sprint and users want to complete the sprint, users can only move them to inactive sprint or backlog. They cannot move them to other active sprints.

Latest ACP-620 Dumps Valid Version with 150 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments