Which of the following best describes a core belief of Agile?

Which of the following best describes a core belief of Agile?
A . The best customer feedback comes near the end of the project when there is working software to review.
B . Project status can be gauged by frequently reviewing completed milestones as reflected in the plan.
C . Working solutions are the most accurate way of seeing the progress of the effort.
D . Unique skill sets are harnessed when team members play different roles on a project.

Answer: C