Agile project development processes typically:

Agile project development processes typically:
A . Encapsulate analysis, design, code, and test within an iteration.
B . Document each business process individually and in detail.
C . Use a Gantt chart with well-defined activities, responsibilities, and time frames.
D . Map the iteration backlog to a Work Breakdown Structure (WBS).

Answer: A