The term “last responsible moment” refers to the moment at which:

The term “last responsible moment” refers to the moment at which:
A . the iteration testing deadline arrives and code testing must stop.
B . failing to make a decision eliminates an important alternative.
C . release planning is complete and the first iteration planning starts.
D . the implementation date is set and sponsor approval has been received.

Answer: B