Which decision role was used?

The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.

Which decision role was used?
A . Majority
B . Consensus
C . Unanimity
D . Plurality

Answer: D