How should the business analyst obtain approval?

A business analyst is working on a system enhancement project and has completed the requirements according to the requirements management plan. The business analyst is now ready to request approval from the stakeholders.

How should the business analyst obtain approval?
A . Provide a defect tracking log for review.
B . Conduct a formal or informal review of the requirements.
C . Send an email requesting approval of requirements.
D . Create and maintain an audit history log of changes to requirements.

Answer: B