Which date formula should you use?
You are creating payment terms.
A company processes standard vendor payments on the seventh day of the next month.
You need to set up payment terms for the vendor.
Which date formula should you use?
A . 37D
B . 1M+7D
C . 1M+6D
D . CM+7D
Answer: D
Explanation: