Which date formula should you use?

You are creating payment terms.

A company processes standard vendor payments on the seventh day of the next month.

You need to set up payment terms for the vendor.

Which date formula should you use?
A . 37D
B . 1M+7D
C . 1M+6D
D . CM+7D

Answer: D

Explanation:

Reference: https://business-central.to-increase.com/md/en-US/ui-enter-date-ranges