When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?

The only output of qualitative risk analysis is risk register updates.

When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?
A . Trends in qualitative risk analysis
B . Risk probability-impact matrix
C . Risks grouped by categories
D . Watchlist of low-priority risks

Answer: B

Explanation:

The risk matrix is not included as part of the risk register updates. There are seven things that can be updated in the risk register as a result of qualitative risk analysis: relating ranking of project risks, risks grouped by categories, causes of risks, list of near-term risks, risks requiring additional analysis, watchlist of low-priority risks, trends in qualitative risk analysis.

Incorrect Answers:

A: Trends in qualitative risk analysis are part of the risk register updates.

C: Risks grouped by categories are part of the risk register updates.

D: Watchlist of low-priority risks is part of the risk register updates.