What system can help you introduce and execute the stakeholder change request with the vendor?

You are working with a vendor on your project. A stakeholder has requested a change for the project, which will add value to the project deliverables. The vendor that you’re working with on the project will be affected by the change.

What system can help you introduce and execute the stakeholder change request with the vendor?
A . Contract change control system
B . Scope change control system
C . Cost change control system
D . Schedule change control system

Answer: A

Explanation:

The contract change control system is part of the project’s change control system. It addresses changes with the vendor that may affect the project contract. Change control system, a part of the configuration management system, is a collection of formal documented procedures that define how project deliverables and documentation will be controlled, changed, and approved.

Incorrect Answers:

B: The scope may change because of the stakeholder change request. Vendor’s relationship to the project, hence this choice is not the best answer.

C: The cost change control system manages changes to costs in the project.

D: There is no indication that the change could affect the project schedule.

Latest CRISC Dumps Valid Version with 933 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments