What should you do?
You restore Resource Schedule Optimization. You need to optimize individual resource schedules.
What should you do?
A . In Field Service Administration, locate a Resource record and select Optimize Schedule.
B . From the schedule board, right-click a Resource record and select Optimize Schedule.
C . From the schedule board, click Actions and select Optimize Schedule.
D . In Resource Schedule Optimization, locate a User record and select Optimize Schedule.
Answer: C