What reservation type should be used?
A maintenance planner is in the process of planning time sensitive emergency maintenance work orders for a number of assets where items need to be reserved.
What reservation type should be used?
A . Soft
B . Hard
C . Urgent
D . Critical
Answer: B
Explanation:
Reference: http://www-01.ibm.com/support/docview.wss?uid=swg21580188