What function on a job plan makes this possible?

The supervisor has specified that the job plans be constructed so that the tasks on the work order will automatically start when the preceding task is complete.

What function on a job plan makes this possible?
A . Workflow
B . Conditions
C . Revisioning
D . Flow Control

Answer: D

Explanation:

Reference: http://www-01.ibm.com/support/docview.wss?uid=swg21327119