What is the best way to address design work that is longer than a single Sprint? (choose the best answer)

What is the best way to address design work that is longer than a single Sprint? (choose the best answer)
A . Breakdown the design work into smaller pieces of work such that they can be ‘done’ within a Sprint.
B. Run design Sprints prior to the delivery Sprints and only work on development after the discovery track is complete.
C. Design work should be completed before the first Sprint can begin.
D. Have the UX Designer work with the Product Owner to help with gathering user data to build and
order the Product Backlog.

Answer: A

Explanation:

There is no role called UX Designer in Scrum. Having a person work with the PO to build and order the PB does not necessarily result in smaller backlog items. Having said that, regardless of whether the items are specific to a component or not, they should be small enough to be completed within a Sprint.

How this is done is up to the Scrum Team.