The most significant reason for using key performance indicators (KPI) to track IT projects against their initial goals is?
The most significant reason for using key performance indicators (KPI) to track IT projects against their initial goals is?
A . Decisions affecting management outsourcing IT projects
B . Identify which projects may require additional funding
C . Identify situations in which stakeholder involvement needs to be strengthened
D . Provide timely instructions on when corrective action is required
Answer: D