In which of the following SDLC phases would the IS auditor expect to find that controls have been incorporated into system specifications?

In which of the following SDLC phases would the IS auditor expect to find that controls have been incorporated into system specifications?
A . Development
B . Implementation
C . Design
D . Feasibility

Answer: B