Which of the following activities are associated with the closing phase of a project? (Choose two.)
Which of the following activities are associated with the closing phase of a project? (Choose two.)A . Risk mitigationB . Archiving of project documentsC . Tracking of expendituresD . Lessons learnedE . Quality assuranceView AnswerAnswer: B,D Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p....
Which of the following activities should be done FIRST?
A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?A . Add durations.B . Add the start and finish datesC . Add tasks.D . Add resources.View AnswerAnswer: C
Which of the following should be the project manager’s NEXT steps?
A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager’s NEXT steps? (Choose two.)A . The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.B . The...
Which of the following are critical for the project manager to provide?
A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?A . Cost, schedule, organizational chart, and risks/issuesB . Risks/issues,...
Which of the following tasks will take place during this phase?
A project is in the initiation phase. Which of the following tasks will take place during this phase?A . Develop a WBC . Define the project requirements.D . Create a project charter.E . Acquire the project resources.View AnswerAnswer: C
When a project team is productive and effective this phase is known as which of the following?
When forming a project team, there are a number of phases. When a project team is productive and effective this phase is known as which of the following?A . FormingB . NormingC . PerformingD . StormingView AnswerAnswer: C
Which of the following tasks are on the critical path?
There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are on the critical path?A . A, C,...
Which of the following risk strategies should the project manager adopt?
A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success. Which of the following risk strategies should the project manager adopt?A . ExploitationB . AvoidanceC . AcceptanceD . MitigationView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA...
In which of the following phases is the project?
A project manager is creating the WBS. In which of the following phases is the project?A . InitiationB . PlanningC . ExecutionD . ClosingView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?A . Project manager and project schedulerB . Project coordinator and project sponsorC . Project champion and project schedulerD . Project stakeholders and project teamView AnswerAnswer: D...