Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?A . EACB . BACC . TCPID . ETCView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 232

September 17, 2018 No Comments READ MORE +

Which of the following tasks are on the critical path?

There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are on the critical path?A . A, C,...

September 17, 2018 No Comments READ MORE +

This action is known as which of the following?

A business has implemented a new online performance management tool that allows functional and project managers to rate employees online. This action is known as which of the following?A . Business process changeB . Organizational changeC . Internal reorganizationD . Business continuity planningView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA...

September 14, 2018 No Comments READ MORE +

Which of the following should have occurred to prevent this issue?

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the...

September 14, 2018 No Comments READ MORE +

Which of the following should the project manager notify?

A milestone task on the critical path has been completed. Which of the following should the project manager notify?A . Owner of predecessor taskB . Project teamC . Project sponsorD . Project steering committeeView AnswerAnswer: C

August 25, 2018 No Comments READ MORE +

Which of the following is a necessary step to record the actual durations?

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?A . Establish each WBS work package resource.B . Establish and set the baseline.C . Establish and set the...

August 24, 2018 No Comments READ MORE +