In which of the following components of the project plan should this be documented?

A project has just finished performance testing and found that the application can only handle 100 concurrent users where the requirement was to handle 500 concurrent users. In which of the following components of the project plan should this be documented?A . Scope statementB . Issues logC . WBSD ....

March 27, 2022 No Comments READ MORE +

Which of the following is a schedule that illustrates the duration of an activity?

Which of the following is a schedule that illustrates the duration of an activity?A . Process diagramB . Ishikawa diagramC . Gantt chartD . Pareto chartView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 168

March 26, 2022 No Comments READ MORE +

Which of the following should be the project manager’s NEXT steps?

A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager’s NEXT steps? (Choose two.)A . The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.B . The...

March 26, 2022 No Comments READ MORE +

When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?

When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?A . Issue logB . Risk management planC . Communications planD . Risk registerE . Status reportView AnswerAnswer: D

March 26, 2022 No Comments READ MORE +

Which of the following tasks are on the critical path?

There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are on the critical path?A . A, C,...

March 26, 2022 No Comments READ MORE +

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?A . EACB . BACC . TCPID . ETCView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 232

March 25, 2022 No Comments READ MORE +

Which of the following actions should the project manager take?

During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take?A . Alert the project sponsor of the situation.B . Contact the customer...

March 25, 2022 No Comments READ MORE +

Which of the following documents did the project manager fail to reference?

An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?A . MOUB . MOAC . SOWD . SLAView AnswerAnswer: B

March 25, 2022 No Comments READ MORE +

Which of the following factors is the MOST likely cause for this scenario?

The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?A . Personal preferenceB ....

March 25, 2022 No Comments READ MORE +

Which of the following types of risk strategies is this an example of?

A risk with a high probability and medium consequence to a project has been identified. In response, the project manager has purchased an insurance plan with the intent to provide additional funds if the risk is realized. There is no risk to the schedule or scope. Which of the following...

March 25, 2022 No Comments READ MORE +