Scrum SSM SAFe 5 Scrum Master (SSM) Online Training
Scrum SSM Online Training
The questions for SSM were last updated at May 07,2024.
- Exam Code: SSM
- Exam Name: SAFe 5 Scrum Master (SSM)
- Certification Provider: Scrum
- Latest update: May 07,2024
What is the main reason why some teams never reach stage 4 in the stages of high performing teams?
- A . because no one guides them
- B . leadership is spontaneous
- C . team is not structured correctly
- D . there is too much conflict
What is the recommended duration of a SAFe iteration?
- A . 2 weeks
- B . 3 weeks
- C . 4 weeks
- D . it depends
Participating in PI planning enables teams to gain alignment and commitment around a clear set of what?
- A . team dependencies
- B . prioritized objectives
- C . user stories
- D . features and benefits
How are the 3 Whys used?
- A . to identify a root cause of a problem
- B . to brainstorm ideas
- C . to coach a team through powerful questions
- D . to define acceptance criteria for a story
There are two primary aspects of a lean-agile mindset lean thinking and what?
- A . feature enablement
- B . lean systems
- C . systems engineering
- D . embracing agility
In SAFe, who owns the decision for releasing changes into production?
- A . product management
- B . system architect
- C . release train engineer
- D . solution owner
During PI planning who owns the planning of stories into iterations?
- A . Agile teams
- B . product management
- C . system architect
- D . scrum master
Which statement is true about the phase-gate milestone model and risk reduction?
- A . It does not mitigate risk as intended
- B . It creates large batches of requirements
- C . It reduces product increment values
- D . It helps to visualize and limit WIP
A
Explanation:
https://www.scaledagileframework.com/base-milestones-on-objective-evaluation-of-working-systems/
When does the Inspect and Adapt event happen?
- A . At the end of the System Demo
- B . At the end of every two weeks
- C . At the end of the second day of PI Planning
- D . At the end of each PI
D
Explanation:
https://www.scaledagileframework.com/inspect-and-adapt/
Who reviews the top capabilities for the upcoming PI?
- A . Project Manager
- B . Solution Architect/Engineer
- C . Solution Management
- D . Project Owner
C
Explanation:
https://www.scaledagileframework.com/product-and-solution-management/