Does the solution meet the goal?

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution. Determine whether the solution meets the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

An electrical engineering company is implementing Dynamics 365 Customer Service.

Engineers schedule work in one-hour blocks.

Engineers who complete a job before the end of the one-hour block must not be able to start a new job in that some block.

Engineers who require part of an additional one-hour block to complete a job must not be able to start a new job in that additional block.

You need to configure the fulfillment preference to meet the requirements.

Proposed solution: Configure the working hours calendar to allow one-hour resource booking blocks.

Does the solution meet the goal?
A . Yes
B. No

Answer: B

Explanation:

Instead: Proposed solution: Create a fulfillment record and set the interval to one hour.

Note: Fulfillment preferences are customizable entities that let you choose how schedule assistant results are displayed, like with neat hourly appointments or morning and afternoon time windows.

By default, the schedule assistant displays results based entirely on resource schedules and the earliest available time, such as 10:39 AM. With fulfillment preferences set to hourly, the same resource’s availability shows as 11:00 AM. This makes it simpler for the scheduler to view and understand availability and communicate it to the customer.

Intervals

Intervals display schedule assistant results in neat time slots that dictate start time of subsequent bookings. When configured as 30-minute intervals, the schedule assistant will display a resource available at 9:27 AM as available at 9:30 AM and will book the start time (arrival time) for 9:30 AM. This includes travel time for onsite requirements and work orders, meaning travel time will begin before 9:30 AM, and a field resource will arrive and start work at 9:30 AM.

Explanation:

Reference: https://docs.microsoft.com/en-us/dynamics365/field-service/set-up-time-groups