The overall progress report for the project indicates that the project is proceeding as planned. However, progress reports from project grouping do not support this.

 The overall progress report for the project indicates that the project is proceeding as planned. However, progress reports from project grouping do not support this.

The biggest risk from this situation may be:
A . The project may not be completed in the safe period
B . User involvement may be insufficient.
C . The project may exceed the cost budget.
D . The Steering Committee may make an inappropriate decision.

Answer: D