Which of the following is the biggest risk?
Due to cost constraints, the company postponed the replacement date for supporting core application hardware.
Which of the following is the biggest risk?
A . The final replacement cost may be higher
B . System availability may be affected
C . Maintenance costs may increase
D . May not be upgraded in the future
Answer: B