In this scenario, what are three examples of data required from the customer?

You are preparing for the installation of a new 2-node switchless AFF A250 ONTAP 9.8 cluster and need to obtain the preinstallation information from the customer.

In this scenario, what are three examples of data required from the customer? (Choose three.)
A . management IP addresses
B. cluster switch name
C. gateway IP address
D. BMC IP addresses
E. cluster name

Answer: A,C,D

Explanation:

Reference: https://docs.netapp.com/us-en/ontap-systems/a250/install-detailed-guide.html#step-1-prepare-for-installation