When should a dependency be raised as a program risk?
When should a dependency be raised as a program risk?
A . When it must be accepted
B. When an Enabler can fix itqueja
C. When it can be resolved
Answer: A
Explanation:
Read more: https://www.scaledagileframework.com/pi-planning/