Communicating the Vision to the Agile Release Train during Program Increment Planning supports which SAFe Core Value?

Communicating the Vision to the Agile Release Train during Program Increment Planning supports which SAFe Core Value?
A . Program Execution
B. Alignment
C. Transparency

Answer: B

Explanation:

Read more: https://www.scaledagileframework.com/safe-core-values/

Latest POPM Practice Questions with 180 Q&As

Updated Study Material | Instant Download | Detailed Answers and Explanations

Subscribe
Notify of
guest
0 Comments