Which of the following is most likely to occur if a Scrum Team is using two separate backlogs for Discovery and Delivery work? (choose the best two answers)
Which of the following is most likely to occur if a Scrum Team is using two separate backlogs for Discovery and Delivery work? (choose the best two answers)
A . It will be easier to track discovery versus delivery items.
B. The team will function like two different teams.
C. The team will be more likely to swarm and help where needed.
D. The amount of work done will be equivalent.
Answer: A,B
Explanation:
Having separate backlogs can make it easier to differentiate the work as the work is now in separate silos but it will also make the team function as 2 separate teams as they would be working from separate backlogs.