Why is this a bad idea?
The Agile Release Train (ART) is near the end of the final Iteration of their first Program Increment. Integration into staging is more challenging than estimated. They add a week to the Innovation and Planning (IP) Iteration for integration and testing.
Why is this a bad idea?
A . Overall train velocity goes up and the time-to-market goes down
B. It substantially decreases the predictability of the Solution Intent
C. It reduces the overall predictability established through cadence and synchroniza-tion
D. It decreases job satisfaction by removing autonomy and purpose
Answer: C