Which would be the appropriate action to enable them to run IBM Wave?

A customer has a zBC12 running Linux on z Systems under KVM. They learned about IBM Wave and how this tool makes it easier to manage, monitor (real-time), and provision Linux guests on z Systems.

Which would be the appropriate action to enable them to run IBM Wave?
A . Enable SIMD on the zBC12.
B . Upgrade from the zBC12 to a z13s.
C . Order additional 3 IFLs on the zBC12.
D . Replace KVM with z/V

Answer: D

Explanation:

IBM Wave for z/VM is a provisioning and productivity management solution for managing virtual servers with z/VM.

The IBM Wave interface provides an innovative approach to the task of managing one or multiple IBM Z systems . Each system can be configured with one or many z/VM instances that can each run virtual Linux servers.

References: https://www.ibm.com/support/knowledgecenter/en/SS6JTX/waveadmin/wave_intro_overview.html