What action should the technical specialist take to ensure a proper installation?

A customer is planning for the installation of a new LinuxONE Emperor processor. The customer specified Balanced Power Plan Ahead (two line cord pairs). At installation time, they advise that they have only been able to provide power outlets for a single line cord pair. They still want the installation to proceed.

What action should the technical specialist take to ensure a proper installation?
A . Advise the customer that the installation cannot proceed until all the configured line cords can be connected.
B . Request the installation engineer to proceed with the installation with a single line cord pair.
C . Request the installation engineer to proceed with the installation of one line cord from each pair to the available power outlets.
D . Create an MES order to remove the Balanced Power Plan Ahead feature until after the installation is complete, then another MES to add the Balanced Power Plan Ahead feature once the extra power outlets are available.

Answer: D

Explanation:

https://www.ibm.com/support/knowledgecenter/5148-21L/p8haj/hmcinstall.htm

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments