Which two steps should the architect include within the implementation plan to ensure a successful deployment of vRealize Automation?

A cloud architect is writing an implementation plan for deployment of a clustered vRealize Automation deployment that will use a third-party load balancer.

Which two steps should the architect include within the implementation plan to ensure a successful deployment of vRealize Automation? (Choose two.)
A . Disable all secondary nodes from the load balancer pools
B. Create and configure the monitoring of vRealize Automation and vRealize Orchestrator
C. Ensure all the SAN certificates for vRealize Suite are available
D. Enable all non-primary nodes on the load balancer
E. Turn off the health monitors or change them temporarily to default to ICMP and ensure traffic is still forwarding to the primary node

Answer: AE

Explanation:

Reference: https://docs.vmware.com/en/VMware-Validated-Design/6.1/sddc-deployment-of-cloud-operationsand-automation-in-the-first-region/GUID-18A6AEF4-2EF7-47B2-B421-D34156344652.html