Which two steps are required for this migration and cutover?

You plan to use Foreign LUN Import (FLI) to migrate data from an older storage array to an ONTAP cluster. You have properly cabled the storage array and the NetApp nodes to your dual-fabric SAN.

Which two steps are required for this migration and cutover? (Choose two.)
A . Add NetApp WWN initiator ports to the existing zones.
B . Add NetApp WWN target ports to the existing zones so that your hosts can access both storage arrays.
C . Create two zones that contain the NetApp target ports and the host initiators ports, one for each fabric.
D . Create two zones that contain NetApp initiator ports and the source storage target ports, one for each fabric.

Answer: BC

Latest NS0-519 Dumps Valid Version with 60 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments