Which two command sequences must be configured on a switch to establish a Layer 3 EtherChannel with an open-standard protocol? (Choose two.)

Which two command sequences must be configured on a switch to establish a Layer 3 EtherChannel with an open-standard protocol? (Choose two.)
A . interface GigabitEthernet0/0/1
channel-group 10 mode auto
B . interface GigabitEthernet0/0/1
channel-group 10 mode on
C . interface port-channel 10
no switchport
ip address 172.16.0.1 255.255.255.0
D . interface GigabitEthernet0/0/1
channel-group 10 mode active

E . interface port-channel 10
switchport
switchport mode trunk

Answer: DE

Latest 200-301 Dumps Valid Version with 489 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
1 Comment
Inline Feedbacks
View all comments
Aaron
Aaron
3 years ago

Should be C and D

C . interface port-channel 10
no switchport
ip address 172.16.0.1 255.255.255.0

D . interface GigabitEthernet0/0/1
channel-group 10 mode active